News

May 2013

A Technical Delegation from South Korea Visited MPL

A Technical Delegation from South Korea representing by the companies M/S SAMAN Engineering (Designer for EPC Consortium), M/S DOHWA Engineering (Proposed Owner’s Engineer Consortium Partner) and KOSEP (Parent Company) visited MPL office to discuss the matter relating to EPC Basic Design and EPC Price. The meeting held in a friendly atmosphere and parties decided to […]

April 2013

Opening Ceremony of Mira Power Limited Corporate Office

Formal Opening Ceremony of Mira Power corporate office was held on April 16, 2013 at 11:30 pm. Distinguished guests from various stakeholders gratified the occasion including honorable Ambassador of Republic of Korea, Mr. Choi Choong-Joo, Executive Vice President of KOSEP, Mr. Kwon Soon-Young and Director General PPC, Mr. Farooq Haider.
The ceremony commenced with ribbon cutting […]

MPL Management meeting with Country Director of Montgomery Watson Harza (MWH)

MPL management had a meeting with Country Director of Montgomery Watson Harza (MWH) in Lahore to discuss the possible role and participation of MWH in Owner’s engineering arrangements for Gulpur Hydropower Project. It was decided to enter into an MOU for the resolution of technical issues in hand until the finalization of overall Owner’s Engineering […]

MPL Management meeting with Acting Member Power of WAPDA

Management of Mira Power Limited had a courtesy meeting with Acting Member Power of WAPDA and discussed the matters of mutual interest about the Gulpur Hydropower Project. Member Power was briefed about the Sponsors of the Project and status of the Project. Member Power appreciated the initiative of Mira Power and ensured his support for […]

MPL Management meeting with Managing Director of NTDC

Mira Power Limited management had a courtesy meeting with Managing Director of National Transmission and Despatch Company (NTDC). Both parties discussed the matters of mutual interest. CEO briefed the Managing Director about the progress on the Project. The matter of interconnection and power evacuation was discussed in detail and NTDC assured their full cooperation to […]

MPL Management meeting with Chairman WAPDA

Mira Power Limited management had a courtesy meeting with honorable Chairman WAPDA at WAPDA House, Lahore. CEO Mira Power briefed the honorable Chairman on the status of Gulpur Hydropower Project and requested for WAPDA support and cooperation. Honorable Chairman WAPDA appreciated the initiative of Korean companies to invest in Pakistan and ensured WAPDA’s support and […]

Meeting with ADB Safeguard Team

The ADB’s social safeguard & environment team visited MPL’s Office today on April 5, 2013 to discuss environment, social and resettlement aspects of the Gulpur Hydropower Project.
The MPL briefed ADB team regarding the Project, its environmental & social impacts along with the mitigation plan and current progress of studies/reports required to be completed and submitted […]

Meeting with Sustainable Solutions (Environment Consultant)

MPL’s management conducted meeting with EIA Consultant regarding revision of Environment Impact Assessment Study, Resettlement Action Plan in accordance with ADB safeguard policies and IFC performance standards on environment.

Meeting with NTDC (Power Purchaser) on Interconnection and Transmission Facility

The Mira Power Limited delegation visited the Planning Department of National Transmission and Despatch Company (NTDC) and meet with General Manager Planning and other representatives of NTDC. They discussed the Interconnection and Transmission Facility of Gulpur Hydropower Project. Mr. Wasim Yousaf, Manager Planning NTDC introduced the necessity of the studies required for interconnection and transmission. The […]

March 2013

Meeting with ADB regarding Project Status and Way Forward

Asian Development Bank representatives attended meeting in MPL’s Office today and apprised regarding initial management approval and next steps for finalization of ADB’s portion of Debt Financing.
MPL explained ADB regarding current status and future program of activities on EPC finalization, financing status of other multilateral financial institutions, concession documents, environment & social assessment, resettlement action plan and […]