The ADB’s social safeguard & environment team visited MPL’s Office today on April 5, 2013 to discuss environment, social and resettlement aspects of the Gulpur Hydropower Project.
The MPL briefed ADB team regarding the Project, its environmental & social impacts along with the mitigation plan and current progress of studies/reports required to be completed and submitted as per ADB’s Safeguard Policy Statement.